Boiler failure after refurbishment requires fast temporary replacement

The Challenge

Following the extensive refurbishment of a leisure centre the building’s on-site boiler failed and a quick replacement was needed fast.

The Solution

After an on-site assessment a 1,3MW boiler was delivered and installed within 24 hours. The heating only boiler provided hot water to a plate heat exchanger. Its low noise design proved to be ideal as local housing backed onto the swimming pool’s site.

[show_gallery /]

The Result

The centre was soon after able to reopen and provide a popular service to the local community.

[testimonial name=”ICS Cool Energy”]“Our 1.3MW boiler is energy efficient providing excellent economy and is housed in a lockable ISO container which is so important on sites where the public are present.”[/testimonial]